COUNCIL COMMUNITY DEVELOPMENT ASPIRATIONS & STRATEGIES PLAN FOR THE NEXT 3 YEARS
Objectives: Senior Staff Housing
Urgent request for 2 x 3 b/r senior staff houses in 2003/04 funding requesting is $180,000.00 the following financial year 2004/05 funding requesting is $190,000.00
Objectives:NARS funding re: Major renovations to 26 council houses
2003/04 Anticipated funding requesting is $360, 000.00
2004/05 and 2005/06 Anticipating funding of $340,000.00 each financial year
Objectives: Demolish & remove 6 old derelict homes
2004/05 Anticipated funding requesting is $60,000.00
Objectives: Sealing of the Community Airstrip
2004/05 New works program estimated cost is $400,000.00
Objectives: Lighting at the Airstrip and runway
2004/05 New works program estimated cost is $200,000.00
Objectives: Erection of 2 Ablution Blocks
2004/05/06 New works program estimated cost is $75,000.00 each
Objectives: Water system & Turf Football Oval
2005/06 New works program estimated cost is $120,000.00
Objectives: Trees planting & Fencing all council houses
2004/05/06 Anticipated funding required is $119,000.00 each year for the next 3 years
Objectives: Upgrade council workshop, plant & equipment e.g.
2003/04/05 (a) Funding is required to purchase an 8 tonne flat top truck, upgrade council workshop and install workshop equipment e.g., electric saw, tyre repair machine, hoist, and miscellaneous tools etc.
(b) 2004/05/06 Funding is required for the purchase of a grader, front-end loader, 2 x 8 tonne tip trucks.
Objectives: Community Swimming Pool and upgrade basketball court.
2003/04 New and upgrade community projects estimated & $450,000.00
|